Contemporary Art Museum

LEN LYE CENTRE

Len Lye Centre 3D model

Len Lye Centre 3D model

Len Lye Centre 3D model, Patterson Associates Ltd

View from bottom of cinema foundations. November 2013

View from bottom of cinema foundations. November 2013

The view from the bottom of the cinema, looking up to the White Hart, on Queen St, New Plymouth

Len Lye Centre panels by Rivet. November 2013

Len Lye Centre panels by Rivet. November 2013

We are so excited... we have the first stainless steel prototype of the facade curve from Rivet - manufacturers of the Len Lye Centre stainless facade panels! These are created in grade 6 stainless - the actual panels will be grade 8. In the picture you can also see 'designs in progress' of mini granite and stainless maquettes for our Innovator and Guardian levels of support. Watch this space...

Artist impression of the Govett-Brewster Art Gallery/Len Lye Centre exterior

Artist impression of the Govett-Brewster Art Gallery/Len Lye Centre exterior

Patterson Associates Ltd

Cinema foundations

Cinema foundations

Len Lye Centre model. 2012

Len Lye Centre model. 2012

Architect's model of the Len Lye Centre and Govett-Brewster Art Gallery combined facility

Cinema foundations

Cinema foundations

Cinema interior walls being installed

Cinema interior walls being installed

Stainless steel panel prototype by Rivet

Stainless steel panel prototype by Rivet

Photo taken 11 December 2013

The big 350 crane on the job of bringing in panels

The big 350 crane on the job of bringing in panels

Photo taken 13 December 2013

View of the Back wall going up

View of the Back wall going up

With 14 metre-high concrete walls erected, the Len Lye Centre on the corner of Queen and Devon St has now reached its highest point. A steel skeleton, manufactured by local MECO Engineers NZ, is starting to emerge which will soon give structure and height to the interior gallery walls. The construction phase of the art gallery museum is on track, with the archive and cinema now having floors, walls and ceilings at street level. Once the impressive steel framework is installed over the coming weeks, the 14 metre-high, 31 tonne, wavy precast concrete panels, from which the stainless steel facade will hang, will start to arrive from Whanganui each on a long B-Train truck.

Steel skeleton goes up

Steel skeleton goes up

With 14 metre-high concrete walls erected, the Len Lye Centre on the corner of Queen and Devon St has now reached its highest point. A steel skeleton, manufactured by local MECO Engineers NZ, is starting to emerge which will soon give structure and height to the interior gallery walls. The construction phase of the art gallery museum is on track, with the archive and cinema now having floors, walls and ceilings at street level. Once the impressive steel framework is installed over the coming weeks, the 14 metre-high, 31 tonne, wavy precast concrete panels, from which the stainless steel facade will hang, will start to arrive from Whanganui each on a long B-Train truck.

Section of mould to make curved panels, 11 April 2014

Section of mould to make curved panels, 11 April 2014

One section of 14m mould used by Emmett to make curved panels - taken at Rivet just before architect inspection

Len Lye Centre construction, 29 April 2014

Len Lye Centre construction, 29 April 2014

Crane lifts large steel beam into place

Len Lye Centre construction, 2 May 2014

Len Lye Centre construction, 2 May 2014

Wooden templates for the curved concrete panels visible at the bottom of photo

Len Lye Centre construction, 2 May 2014

Len Lye Centre construction, 2 May 2014

Installing the roof over the main gallery

Len Lye Centre construction, 6 May 2014

Len Lye Centre construction, 6 May 2014

Clelands builders assemble steel cross structures for the gallery walls. Photo by Josh Manu.

Len Lye Centre Construction, 9 May 2014

Len Lye Centre Construction, 9 May 2014

Foundations poured. Photo by Bruce Earby.

Architects inspect Mould, 28 May 2014

Architects inspect Mould, 28 May 2014

Architects Andrew Mitchell and Joanna Aitken inspect mould for curved concrete panels at Emmett Civil Construction, Whanganui

Len Lye Centre construction, 2 July 2014

Len Lye Centre construction, 2 July 2014

Concrete foundations being poured. Photo by Keri Naus.

Len Lye Centre Construction, July 2014

Len Lye Centre Construction, July 2014

Curved concrete panels at Emmetts Civil Construction, Whanganui. Photo by Glenn Jeffrey.

Len Lye Centre Construction, July 2014

Len Lye Centre Construction, July 2014

Curved concrete panels at Emmetts Civil Construction, Whanganui. Photo by Glenn Jeffrey.

Len Lye Centre construction, 15 July 2014

Len Lye Centre construction, 15 July 2014

First panel arrives onsite, 28 July 2014

First panel arrives onsite, 28 July 2014

The First concrete curved panel arrives on-site on a truck from Emmetts Civil Construction in Whanganui

First panel going up, 29 July 2014

First panel going up, 29 July 2014

The first curved concrete panel is lifted into place. Photo by Kelly Wells

Len Lye Centre Construction, 30 July 2014

Len Lye Centre Construction, 30 July 2014

Second and Third panels go up. Photo by Glenn Jeffrey.

Len Lye Centre Construction, 30 July 2014

Len Lye Centre Construction, 30 July 2014

Second and Third panels go up. Photo by Glenn Jeffrey

Len Lye Centre Construction, 30 July 2014

Len Lye Centre Construction, 30 July 2014

Second and Third panels go up. Photo by Glenn Jeffrey

Len Lye Centre construction, 5 August 2014

Len Lye Centre construction, 5 August 2014

The third curved concrete panel is lifted into place on the back side of the Len Lye Centre

Len Lye Centre Construction, 19 August 2014

Len Lye Centre Construction, 19 August 2014

Devon Street side panels going up. Photo by Glenn Jeffrey

Len Lye Centre Construction, 19 August 2014

Len Lye Centre Construction, 19 August 2014

Devon Street side panels going up. Photo by Glenn Jeffrey

Len Lye Centre Construction, 19 August 2014

Len Lye Centre Construction, 19 August 2014

Devon Street side panels going up. Photo by Glenn Jeffrey

Len Lye Centre Construction, 22 October 2014

Len Lye Centre Construction, 22 October 2014

All concrete panels installed in place. Photo by Glenn Jeffrey

Len Lye Centre Construction, 22 October 2014

Len Lye Centre Construction, 22 October 2014

All concrete panels installed in place. Photo by Glenn Jeffrey

The first of the stainless steel panels installed, 9 December 2014

The first of the stainless steel panels installed, 9 December 2014

The first of the stainless steel panels that will form the Len Lye Centre’s spectacular facade have been installed. “People won’t see much to start with as this 14-metre section has a protective PVC coating on it for now,” says Chief Operating Officer Sue Davidson. “That coating will be removed in the next few days as the installation progresses.” The facade will be made up of curved stainless steel sections that will hang from the 20 curved concrete panels along Devon and Queen streets. The stainless steel panels will be installed throughout summer. “This is exacting work,” says Ms Davidson. “The first four stainless steel channels that will hold the panels in place are already bolted onto the concrete panels and the insulation between those channels has been fixed into position. Now the slotted steel panels will be hung from metal pins located at intervals down the vertical channels.” A massive skylight was delivered to the site this week, which some members of the public thought was the first steel facade panel. “That skylight will go into the roof of the large works gallery of the Len Lye Centre. It’s designed to be removed by crane so that large art installations of up to nine metres in height can be lifted into the gallery for exhibitions.” Inside the Len Lye Centre, the cinema’s concrete floors are finished and timber framing for the steps and cinema seats has started. Earthquake strengthening on the roof of the Govett-Brewster building is nearing completion. Photo: Glenn Jeffrey

The first of the stainless steel panels installed, 9 December 2014

The first of the stainless steel panels installed, 9 December 2014

The first of the stainless steel panels that will form the Len Lye Centre’s spectacular facade have been installed. “People won’t see much to start with as this 14-metre section has a protective PVC coating on it for now,” says Chief Operating Officer Sue Davidson. “That coating will be removed in the next few days as the installation progresses.” The facade will be made up of curved stainless steel sections that will hang from the 20 curved concrete panels along Devon and Queen streets. The stainless steel panels will be installed throughout summer. “This is exacting work,” says Ms Davidson. “The first four stainless steel channels that will hold the panels in place are already bolted onto the concrete panels and the insulation between those channels has been fixed into position. Now the slotted steel panels will be hung from metal pins located at intervals down the vertical channels.” A massive skylight was delivered to the site this week, which some members of the public thought was the first steel facade panel. “That skylight will go into the roof of the large works gallery of the Len Lye Centre. It’s designed to be removed by crane so that large art installations of up to nine metres in height can be lifted into the gallery for exhibitions.” Inside the Len Lye Centre, the cinema’s concrete floors are finished and timber framing for the steps and cinema seats has started. Earthquake strengthening on the roof of the Govett-Brewster building is nearing completion. Photo: Glenn Jeffrey

The first of the stainless steel panels installed, 9 December 2014

The first of the stainless steel panels installed, 9 December 2014

The first of the stainless steel panels that will form the Len Lye Centre’s spectacular facade have been installed. “People won’t see much to start with as this 14-metre section has a protective PVC coating on it for now,” says Chief Operating Officer Sue Davidson. “That coating will be removed in the next few days as the installation progresses.” The facade will be made up of curved stainless steel sections that will hang from the 20 curved concrete panels along Devon and Queen streets. The stainless steel panels will be installed throughout summer. “This is exacting work,” says Ms Davidson. “The first four stainless steel channels that will hold the panels in place are already bolted onto the concrete panels and the insulation between those channels has been fixed into position. Now the slotted steel panels will be hung from metal pins located at intervals down the vertical channels.” A massive skylight was delivered to the site this week, which some members of the public thought was the first steel facade panel. “That skylight will go into the roof of the large works gallery of the Len Lye Centre. It’s designed to be removed by crane so that large art installations of up to nine metres in height can be lifted into the gallery for exhibitions.” Inside the Len Lye Centre, the cinema’s concrete floors are finished and timber framing for the steps and cinema seats has started. Earthquake strengthening on the roof of the Govett-Brewster building is nearing completion. Photo: Glenn Jeffrey

PreviousPauseNext



The Len Lye Centre will inspire the mind and engage the senses. New Plymouth will be the world centre for the care, display, access to, research and development of the works and ideas of Len Lye, an extraordinary thinker and visionary artist.

Our vision is to offer powerful and memorable experiences generated by the art and ideas of Len Lye. A visionary New Zealander, Lye’s work has enthralled audiences throughout the world since early last century. His ingenuity, expansive creativity and technical brilliance are qualities emblematic of what New Zealanders value. The Len Lye Centre will offer permanent access in an exceptional home that honours the artist, his Collection and Archive and its value for New Zealanders and global visitors.

In June 2011, Hon. Christopher Finlayson, Minister for Arts, Culture and Heritage announced support of $4 million over two years from the Government’s Regional Museums Policy for Capital Construction Costs. This is a major step in making the planned Len Lye Centre a reality.

Internationally  acclaimed architectural firm Patterson Associates is on board as the design architects. Pattersons has developed an inspirational design that’s effective and fit for purpose and will offer a striking new contribution to the architectural landscape of Aotearoa New Zealand. Andrew Patterson, from Patterson Associates, on Close Up TV1 »

For more details on the Len Lye Centre see our FREQUENTLY ASKED QUESTIONS

The Len Lye Centre will be a catalyst for the following conversations:
• Innovation with passion »
• Valuing art, beauty, culture »
• Endless inquiry »
• Transforming minds »

 

‘The Len Lye Centre will demonstrate unequivocally to the world the very best of New Zealand creativity, determination and technical innovation through one of its greatest and most celebrated exponents.' Sir Richard Taylor, Creative Director Weta Workshop, Wellington, 2010.

Len Lye Committee Chair, Cr. Lance Girling-Butcher comments, ‘The Len Lye Centre project will make an outstanding contribution to the quality of life for the people of New Plymouth and will provide a new destination for national and international visitors to Taranaki. The Centre will join the region’s other leading cultural and environmental attractions and strengthen New Plymouth’s unique place as a culturally and economically progressive community.’

The Len Lye Collection and Archive has been under the legal care of the Govett-Brewster Art Gallery since Len Lye bequeathed his entire Collection and Archive to the Len Lye Foundation through a Deed of Trust in 1980. The Govett-Brewster is renown internationally as the home of Len Lye. One in three people that visit the Gallery each year request to see Len Lye's work. To meet this demand while enhancing the care and preservation of this unique, large and fragile collection to global standards, the New Plymouth District Council - in partnership with the Len Lye Foundation - is working towards the realisation of the Len Lye Centre for the benefit of New Plymouth and New Zealand.

The Centre would guarantee permanent access to Lye's work and will consolidate New Plymouth as the world centre for the care, display, research and development of the works and ideas of Len Lye, an extraordinary thinker and visionary artist. The Centre will become a significant cultural attraction for New Zealanders and international visitors to Taranaki.

The site for the Len Lye Centre is in central New Plymouth, on the corner of Devon St West and Queen St, adjacent to and connecting with the Govett-Brewster Art Gallery. This site acknowledges the long association between Len Lye and the Gallery, and maximises the benefits of shared facilities, services, staff and management.

Capital costs for the construction of the Centre will be raised from outside the New Plymouth District Council sources. The annual net operating cost of the Len Lye Centre will be jointly funded through support from sponsorship, revenue generation, fundraising and the New Plymouth District Council. The New Plymouth District Council will own and operate the combined Len Lye Centre and Govett-Brewster Art Gallery.

Plans for New Zealand’s first dedicated single-artist museum include a programme of dynamic exhibitions presenting the full range of Lye’s work encompassing kinetic sculpture, film, painting, photography, book design, batik and writing. The inclusion of a cinema to present Lye’s work alongside other independent filmmakers is planned as well as online access to the Len Lye Collection and Archive. Additionally, the Len Lye Foundation is undertaking the realisation of a several small and large scale kinetic works in accordance with the artist’s intention. Len Lye’s films are officially housed and cared for by New Zealand Film Archive (NZFA) in Wellington as instructed by the artist in the 1980 Deed of Trust.

The legal partnership between the Len Lye Foundation and the New Plymouth District Council - with museum leadership from the Govett-Brewster Art Gallery - is key to the development of the Len Lye Centre for the benefit of all New Zealanders. A partnership programme to secure public and private investment, sponsorship and partnership and fundraising is currently underway towards the realisation of the Len Lye Centre which is planned to open to the public in 2014.

This project is published on www.e-architect.co.uk


Courtney Johnston talks with Kathryn Ryan on Radio NZ's Nine to Noon about Len Lye


Radio New Zealand Morning Report, Tuesday 29 July 2014: The first of the 14-metre-high panels that are part of the new stainless steel facade of New Plymouth's Len Lye Centre will be erected today.



On Radio NZ's The Arts on Sunday, Lynn Freeman talks with Len Lye Comittee Chairman Lance Girling-Butcher and Govett-Brewster Art Gallery Director Rhana Devenport about the Len Lye Centre.